MWAA Announces Delay in Silver Line Completion

Delay due to safety testing concerns is expected to take several weeks.

MWAA has announced a delay in the Silver Line, due to the need for additional testing.
MWAA has announced a delay in the Silver Line, due to the need for additional testing.
By Alex McVeigh

The Metropolitan Washington Airports Authority announced Monday that additional tests are needed on Phase One of the Silver Line, focusing on software updates related to the Automatic Train Control System, before the project can be turned over to the Washington Metropolitan Area Transit Authority.

Recent testing of the Silver Line in preparation for substantial completion has identified needed software modifications to the Automatic Train Control System.

The contractor is in the process of making the changes to ensure the proper performance of the train control system. Once completed, the contractor will produce a summary of the changes made for review and approval by WMATA and the Airports Authority.

This will be followed by re-testing to make sure the system is functioning properly and meets performance specifications.

The Airports Authority is awaiting a definitive schedule from the contractor for the additional activity.

The additional activity is expected to take several weeks to complete. Substantial completion of the project will be determined as results from the testing are obtained.

"This is why we test," said Pat Nowakowski, executive director of the Dulles Corridor Metrorail Project in press release. "Our guiding principle throughout this process has been ‘safety first’ and we remain committed to that principal. We will not do anything that might compromise safety or create unsafe conditions for the traveling public."

At the Nov. 16 meeting of the Airports Authority Board of Directors, Nowakowski reported that final testing was underway on Phase One of the Silver Line.

Based on information available at that time, the expectation was that the contractor would declare substantial completion before the end of the month.

But Nowakowski also pointed out that any problems identified during the testing could potentially delay that schedule.

The Silver Line is being built in partnership with Loudoun and Fairfax counties and the Commonwealth of Virginia, and will be transferred to the WMATA for operation upon completion.

Phase One consists of four stations in Tysons Corner, as well as one at Wiehle Avenue and the Dulles Toll Road.

Phase Two will continue west along the toll road through Dulles Airport before terminating in Ashburn, and will include a stop in Herndon.


FOLLOW HERNDON PATCH FOR THE LATEST NEWS AND EVENTS!

Facebook | Twitter | Daily & Breaking News E-mail Updates

Dan French December 04, 2013 at 02:21 PM
So yet another delay, this time due to software issues? Why should there be any software problems since this is a new line on an existing system? Wouldn't they just be using the existing system software, which is safe enough for the rest of the metro system?

Boards

More »
Got a question? Something on your mind? Talk to your community, directly.
Note Article
Just a short thought to get the word out quickly about anything in your neighborhood.
Share something with your neighbors.What's on your mind?What's on your mind?Make an announcement, speak your mind, or sell somethingPost something