patching...
Update: Only 2 more "likes" until we reach 1,600! Have you liked Herndon Patch on Facebook yet? If not, you're missing the conversation! CLICK HERE »
Welcome back, Patch Blogger!

IG Report Questions MWAA Policies

In statement, regional panel welcomes report, while letter to LaHood criticizes interference.

 

A long-awaited report about the Metropolitan Washington Airports Authority by the U.S. Secretary of Transportation’s Inspector General calls for actions beyond what the regional panel has already undertaken.

MWAA, responsible for constructing Metro’ Silver Line project from Falls Church to Ashburn, came under fire for lax oversight of its members. The IG report also raises questions about whether the organization’s policies permit favoritism in awarding contracts and nepotism in awarding jobs.

For the full report, see the PDF attached to this article.

After an interim report from the IG, MWAA approved a new travel policy and code of ethics, revised bylaws for board members and its Freedom of Information Policy and terminated contracts with former board members. But the IG’s final report finds those measures inadequate.

“While these are the types of actions needed to ensure fiduciary and ethical responsibility, further actions remain to fully address the management weaknesses we identified during our audit,” a summary of the report states.

A response to the report from MWAA on Thursday appears to show the organization is prepared to accept the criticism and work with the U.S. Secretary of Transportation Ray LaHood to make improvements.

“While the criticisms and issues raised have been unpleasant to hear – and will require hard work to address – we appreciate their interest and guidance, and we know they share our goal of making the Airports Authority a better organization,” MWAA said in a press release.

But the statement falls in stark contract with a letter sent one month earlier by MWAA board member Robert Clarke Brown to LaHood (see attached PDF), in which he charged the secretary with overstepping his bounds and requests the government shift its focus from investigating MWAA to helping fund the Silver Line, which currently relies primarily on tolls along the Dulles Toll Road. The tolls are expected to rise significantly if an additional infusion of money cannot be found. In fact, Brown praises the work of MWAA, disregarding the issues raised by the IG report.

“The Metropolitan Washing Airports Authority is a triumph of good transportation policy, a vivid demonstration of what a regional approach can accomplish in a large metropolitan area,” Brown wrote. “Not only have your repeated encroachments on MWAA’s independence been of questionable lawfulness, they have also gone far beyond the traditional role of U.S. DOT in local project development and execution.”

Brown went on to add that “most members” of the MWAA board “believed the Inspector General was acting far beyond the scope of his legal authority.”

In Brown’s letter, sent on MWAA letterhead, he acknowledges that the criticisms of the organization “have not been without merit,” but “I urge you now to turn your efforts on behalf of the Silver Line away from local politics and yesterday’s governance problems, and toward the real challenge the project still faces.”

Those problems were identified as securing state and federal funding for the project. The federal government contributed $900 million to the project’s first phase, about one-third of the cost. No federal money has been allocated for phase two, estimated to cost an additional $2.7 billion.

The procurement process for phase two has begun, while passengers are expected to begin board trains from phase one stations next year.

Related Topics: Ashburn Metro, Dulles Corridor Metrorail Project, MWAA, and Silver Line

Bob Bruhns

5:25 pm on Friday, November 2, 2012

I have reported many times that the cost of the Dulles Rail project appears to be about two times what it should be.
http://www.bruhns.us/civic/DullesRail/Dulles-Rail—Silver-Line-overcost-report—Bruhns.pdf

Now comes this US DOT audit report that shows one big reason for the Dulles Rail double price that I have noted. The audit reports that MWAA has been steering a large percentage of multi-award contracts to a contractor that apparently charges 1.3 to 3.3 times as much as other contractors.

I submit that because of the size of the Dulles Rail project, the magnitude of the cost increase caused by this practice will crush the economy of this region for much of this century. I hope that the people who pushed for this rail project without regard to its cost, and our so-called ‘leaders’ and news media that covered up the double price of Dulles Rail (also known as the Silver Line) all these years, are proud of themselves.

Maybe it is not too late to force Phase II of this project, at least, to be contracted properly and at a reasonable cost. Our government should also vigorously pursue the recovery of excessive payments that were made for Phase I.

(continued)

Reply
Comment_arrow

Bob Bruhns

5:26 pm on Friday, November 2, 2012

US DOT Audit Summary:
http://www.oig.dot.gov/library-item/5979

US DOT Audit Report:
http://www.oig.dot.gov/sites/dot/files/MWAA%20Final%20Report.pdf

From the top of page 14 of the audit report (page 15 of the pdf):
“Over the past 8 years, MWAA awarded more than 80 percent of work under three groups of multiple-award contracts to a single contractor (“Contractor A” in table 2). However, the contractor’s rates were often higher than the other multiple-award contractors’ rates. For example, the contractor’s rates in a 2012 contract were between 28 percent and 234 percent higher. While MWAA may have had non-price related reasons for selecting Contractor A, this unbalanced distribution of work to a single contractor with significantly higher rates appears contrary to the purpose of multiple-award contracts and could further compromise MWAA’s competitive environment. ”

And from further down that page:
“In addition, MWAA allowed Contractor A to add job categories to a contract but did not offer the other multiple-award contractors the same opportunity. Thus, when MWAA ordered work related to those additional job categories, they were effectively sole source awards because only one contractor was able to accept the work. “

Comment_arrow

Just the Facts

9:48 am on Tuesday, November 6, 2012

Who was the contractor who benefited? Why was this not disclosed? What favors did this contractor give the employees of MWAA? Why is Wolf, LaHood and McDonnell not asking these questions? This smells and we are all going to pay for this in higher tolls.

the-stix

8:19 pm on Friday, November 2, 2012

The Dulles Rail contract is not a multiple award contract (MAC) which was a main focus of the IG's audit. In fact the Phase 1 contract is not a MAC and was not examined, nor is it even mentioned in the report.

If there had been obvious discrepancies in Phase 1 policy and/or procedure it is not unreasonable to assume that the IG would have been more than eager to look at that contract and boldly feature its flaws, and to insist the report findings be especially applied to the high dollar value Phase 2. They did not and therefore to automatically assume based on this report that the Phase 2 estimate is suspect to the tune of being 100 percent overpriced is a complete fantasy.

Reply

Bob Bruhns

12:13 am on Saturday, November 3, 2012

MWAA awarded more than 80% of multiple award contracts at 130% to 330% of the cost of other bids, and you actually think they are being frugal with Dulles Rail? Wake up and smell the coffee, dude! I based my estimate on several things, stix, and this audit result is more confirmation.

Here's a question, stix. You know that the MWAA estimate for the parking garages, for example, is 48% higher than your very generous estimate. Why aren't you saying anything about that?

Please stop being an apologist for the Dulles Rail ripoff.

Reply

the-stix

6:26 am on Saturday, November 3, 2012

Again Phase 1 is NOT a MRC and it was not even reviewed or mentioned in the audit report, even though it is the most prominent MWAA contract today and probably of greatest value.

To leap to the conclusion that the audit report proves your "amateurish" analysis (your words) that the actual incurred cost of Phase 1 and the estimated cost of Phase 2 are each 2X overpriced is an 'ends justify the means' act of a opponent of Dulles Rail that lost his fight to kill Phase 2, imo.

It is noteworthy that no one believes your analysis and off-the-wall 2X allegation but you.

And btw I believe the MWAA estimated garage costs are as accurate as can be reasonably expected of the experienced professional estimators MWAA used. The actual cost of the Rt 28 garage will be known when that portion of the Phase 2 contract is negotiated with the competitively selected Design/Build contractor.

Reply

Jonathan Erickson

7:09 am on Saturday, November 3, 2012

It do appear that the value received for the price paid is way below normal expectations. The IG report states that the MWAA is as corrupt a group as any in the US. No bid contacts, nepotism, travel expenses, dining expenses, hiring practices and no accountability just a few of the less then stellar attributes of the MWAA.

Reply

the-stix

8:47 am on Saturday, November 3, 2012

Although the audit report cites many instances of dubious administrative, human resources and contracting actions in SERVICES areas, it does not even mention the Dulles Rail Phase 1 Design/Build contract. Nor does it include in its 13 recommendations any suggestion that any apply to the pending Phase 2 contract, huge in terms of value and public attention.

That is not to say there are not report recommendations that would benefit the Phase 2 competitive bid and ultimate contract. But to conclude based on the audit report (that has been many months in the preparation and that does not even mention Phase 1 or Phase 2) that we the public are "not getting the value for the price paid" is wholly unwarranted. And to jump to the conclusion as MR. Bruhns has that the report somehow justifies his wild assertion that the current Phase 2 estimate is 2X overpriced is simply ludicrous by any standards.

Reply
Comment_arrow

Bob Bruhns

10:00 am on Thursday, November 8, 2012

Stix, the 3.1 billion dollar cost of the Design-Build contract, plus financing, was mentioned in the second sentence of the report. And the Phase II estimate is mentioned too.

Perhaps you are not aware of MWAA's track record with regard to costs. MWAA will probably not let Phase II go too far above the incredibly bloated cost estimate numbers that they have handed us - but that's not saying much, because they handed us cost figures that are two times what they should be. In case you haven't noticed, MWAA isn't particularly good at lowering costs. That's why the US DOT stepped in, back in 2011. MWAA, the organization that seems to like paying 130% to 330% of what they should spend, happily accepted cost estimates that are simply unjustified, and passed them along to us. Well, except that they seemed to be looking for any way they could think of, to make the numbers even higher. In fact, between July 2011 and March 2012, they managed to hyperinflate the price of the Rt 28 rail station by 22%, and the cost of the parking garages by 29%. That's a big jump, for less than a year of hyperinflation.

Why is it that the items that the Counties have to pay skyrocketed on March 6, 2012, while the rest of the project held about steady? And why didn't the so-called news media happen to mention that?

the-stix

9:27 am on Saturday, November 3, 2012

Dulles Rail, although mentioned only in the opening paragraph of the letter as background, it is nowhere mentioned in the main report, nor was it apparently reviewed, nor is it referenced in any of the detailed recommendations. To jump to the conclusion that thie report as written proves a 2X overprice of the Phase 2 estimate is dumb in my view. Five or ten percent overpriced perhaps since it only an estimate, but 100% has no creditability as demonstrated by no one that has come forward in agreement.

Reply
Comment_arrow

Bob Bruhns

4:44 am on Monday, November 5, 2012

Actually, you will find "Dulles Toll Road and Dulles Metrorail project" mentioned on page 18 of the audit report (page 19 of the pdf). The Inspector General was noting that there are 47 contracts per year from these, over the 2.5 year audit period from January 2009 to June 2011.

That adds up to about 117 contracts. I submit that it is very likely that he was talking about some Dulles Rail contracts in his report, then. But this audit was about MWAA practices in general, not Dulles Rail Phase I or Phase II in particular.

Reviewing this, I found that MWAA awarded 709 contracts between January 2009 and June 2011. See p.16 of the Audit report (p.17 of the pdf), and footnote 14 on p.9 (p.10 of the pdf). Of these, 190 exceeded $200,000 in value. See p.8 of the Audit report (p.9 of the pdf). Of these, 32 were examined in detail. These 32 contracts totalled $251 million in value, an average of $7.84 million each. See p.45 of the Audit report (p.46 of the pdf), Figure 3, Sample 1.

Comment_arrow

Bob Bruhns

4:53 am on Monday, November 5, 2012

Oh - and as you are well aware, my assertion that MWAA's price for the Dulles Rail project is double-priced, is based on examination of the overall Phase II cost compared to another local rail extension job, the cost of the Rt 28 station and the cost of the parking garages compared to similar jobs, and the fact that a Fairfax County official who has access to the cost figures that are deliberately hidden from lowly citizens and taxpayers like us, says that Phase I was priced about the same as the July 3, 2011 Phase II FTA figures. My cost analysis can be found here:
http://www.bruhns.us/civic/DullesRail/Dulles-Rail---Silver-Line-overcost-report---Bruhns.pdf

the-stix

9:46 am on Saturday, November 3, 2012

Your analysis is unprofessional and naïve, but I agree with you in your own assessment that it is “amateurish’. Repeating it hundreds of times as you have in this and local forums does not give it any creditability. I would contend that this is conclusively demonstrated by the fact that no one has come forwards in all these months that is in agreement.

Drop it Mr. Bruhns. Your 2X claim no matter how many times you shout it is bogus. You lost your campaign to kill Phase 2!

Reply

Bob Bruhns

10:25 am on Saturday, November 3, 2012

Well stix, I don't know how many Inspector General reports you need to see, that tell you that MWAA has been happily awarding their contracts at 30% to 230% elevated cost, before you begin to realize that what I'm saying is correct. But ignoring the double cost two thousand times will not make the double price right

Reply

the-stix

11:44 am on Saturday, November 3, 2012

The audit only examined 125 contracts awarded between 1989 and 2011. This is but a fraction of the total number of contracts awarded during that period. In fact there were 190 contracts awarded between 2009 and 2011 alone.

To jump to the conclusion as you have that because of a fraction of the 125 contracts examined had costing discrepancies, that Phase 1 (that they chose not to examine) had similar costing discrepancies is as bogus as your amateurish analysis. Your 2X 'sky is falling' claim is nonsense and the audit report findings say nothing to the contrary. If you were honest, you would recant your first post in this thread.

Reply
Comment_arrow

Bob Bruhns

11:59 am on Sunday, November 4, 2012

So, stix - not only are you attacking my analysis, but you are attacking the Inspector General's audit as well. I'm in good company, it seems.

Jonathan Erickson

6:41 pm on Saturday, November 3, 2012

Thats enough contracts of considerable value that shows mass corruption.

Reply

Bob Bruhns

10:29 pm on Saturday, November 3, 2012

Once again stix: as you are well aware, my conclusion of a roughly 2:1 overcost is based on MWAA's estimates of the overall cost of Phase II, the statement of Mark Canale that Phase I prices were similar to the FTA numbers for Phase II, the cost of the Rt 28 station and the cost of the parking garages.
http://www.bruhns.us/civic/DullesRail/Dulles-Rail---Silver-Line-overcost-report---Bruhns.pdf

You say that my analysis is defective, but then you intimate that the Inspector General's analysis is defective as well. From what you are saying, it seems that I'm in good company!

But the point about this audit is that MWAA routinely awards contracts at prices that are sometimes bloated 3.3 to one - and that supports my claims. I suspect that your evident desperation to mischaracterize the basis of my analysis indicates that it is you who are losing this debate.

On P2 of the audit (P3 of the pdf):
"We conducted our audit in accordance with generally accepted Government auditing standards. To conduct our work, we reviewed relevant acts, agreements, policies, and manuals; examined Federal, State, and local best contracting practices; and interviewed MWAA officials. In addition, we reviewed a total of 125 contracts to evaluate MWAA’s contract practices."

Reply

the-stix

5:20 am on Sunday, November 4, 2012

Here is what Mark Canale said:

“We have actual cost information related to Phase 1 and the cost of these Phase 2 elements are within the range of what the costs we have seen in Phase 1”.

In other words the Phase 2 cost estimate is consistent with the actual costs being experienced on Phase 1. He did NOT endorse your flawed 2x analysis. In fact after all these months of your writing letters and posting hundreds of times, no one has endorsed your analysis.. again NO ONE!

Reply
Comment_arrow

Bob Bruhns

11:55 am on Sunday, November 4, 2012

As you see, Stix, Mr. Canale confirmed that Phase I prices were about the same as the Phase II prices. Since I have demonstrated that Phase II prices are very questionable, that means that Phase I prices are very questionable as well. Thank you for confirming my point.

joe brewer

7:51 am on Sunday, November 4, 2012

Maybe phase 1 should be audited for cost overruns. Didn't they just set up a 150 million dollar slush fund for the pilings in August? Alright just so you lose the repeated talking point I fully agree with Bob on the cost of phase 2. If it's not 2 times as much it's probably more. Tell me about the cost of the garages per space and the rail cars that have increased in price from 2.6 million to 4 million per car Stix.

Reply
Comment_arrow

the-stix

11:24 am on Sunday, November 4, 2012

Thank you, joe brewer for your input. You should know however that it does not change my opinion that 1. the IG report says nothing specific about Dulles Rail costing and/or contractual improprieties and 2 it certainly does not corroborate anything in Mr. Bruhns 2x analysis as he started this thread with.

I will put you down as having read and fully accepting Mr. Bruhns analysis, which assumes his analysis is superior to the Phase 2 estimators AECOM and Parsons Brinkhoff and an independent estimator McDonough, Bolyard and Peck. And I will ask you as I have Mr. Bruhns, what specifically is overpriced in those estimates from professional estimators, experienced in rail projects.

Where are your facts? And please don’t waste time replying what the Phase 2 cost “should” be or what you would “like” it to be. And do not use the ploy of turning the question back to me as to what certain item costs are such as the garages and rail cars. You are presumably convinced in the 2X (or more) overcharge.. tell us where and why your estimate is better than all others.

Comment_arrow

Bob Bruhns

12:09 pm on Sunday, November 4, 2012

Stix knows that the estimates from the estimating companies he cited are non-specific in any documents that are available to the public. However, I have pointed out the excesses in the MWAA estimates for the Phase II parking garages and for the Rt 28 (Innovation) rail station. In fact, stix himself showed the Rt 28 parking garage estimate to be 48% high - that is documented in the eighth post on this page:
http://restonweb.com/forum/viewtopic.php?t=5977&start=45
I'm really not sure why stix continues to pretend that Dulles Rail / Silver Line costs are not massively excessive.

Comment_arrow

the-stix

3:59 pm on Sunday, November 4, 2012

For the record my back-of-the-envelope estimate was within 4% of the MWAA estimate developed by AECOM and Parsons Brinkhoff and the independent estimator McDonough, Bolyard and Peck. I accept their estimates until it is replaced by the accepted pricing of the sucessful Phase 2 Design/Build contractor.

Comment_arrow

Bob Bruhns

8:54 pm on Sunday, November 4, 2012

Stix, the July 3, 2011 FTA Rt 28 parking garage estimate of $53 million (that you cited) is 1.14 times your May 24, 2012 estimate of $46.6 million - so the $53 million estimate was 14% higher than your May 24, 2012 estimate, not 4% as you repeatedly claim.

But it's even worse than that. On March 6, 2012, unnoticed by the news media, our so-called 'leaders', and apparently also by you, MWAA ballooned the parking garage and Rt 28 station costs by 29% and 22% respectively. So, the present MWAA estimate for parking garages means that the Rt 28 parking garage costs $68.9 million, not $53 million - and that March 6, 2012 $68.9 million estimate is indeed 48% higher than your May 24, 2012 $46.6 million estimate. Do the arithmetic.

And consider this. You are saying that the Rt 28 garage cost should be about 2/3 of MWAA's current estimate. Why do you continue to pretend that the Dulles Rail / Silver line project is not massively overpriced?

Comment_arrow

the-stix

6:58 am on Monday, November 5, 2012

My estimate was $51 million vs MWAA's $53 million and at that no better than yours, and especially no better than the rail project experienced and professonal bottom-up Phase 2 estimates of AECOM and Parsons Brinkhoff and an independent estimator McDonough, Bolyard and Peck.

Comment_arrow

Bob Bruhns

2:44 pm on Monday, November 5, 2012

Your estimate was $46.6 million stix. Sorry.

But even if your estimate had been $51.1 million, MWAA (and presumably their estimators) still have you beat, with a $68.9 estimate that is about 35% higher than your $51.1 million figure. Weren't you saying that the error could not be more than 5% to 10%?

So, are you going to ratchet up your estimate again? Why not? Heck, MWAA ratcheted their estimate up 29% between July 3, 2011 and March 6, 2012.

Comment_arrow

the-stix

3:07 pm on Monday, November 5, 2012

Yes $46.6 million PLUS cost escalation out to the anticipated mid-point of the construction project, if they followed standard costing practice. At the indices MWAA had been using, that would be an additional $4.4 million.

For even the simple minded, $46.6 million plus $4.4 million equals $51 million (my estimate) which is about 4% lower than the MWAA estimate at the time of $53 million. Get it Mr. Bruhns, or shoud I write it all in capital letters next time?

Comment_arrow

Bob Bruhns

4:39 pm on Monday, November 5, 2012

Ha ha, OK, but even if you say $51.1. million, MWAA's estimate is 35% higher than yours. And you think 5% to 10% should be the limit of error. Now, unless MWAA isn't conforming to your midpoint cost estimate, that's about all there is to it, stix. You are saying that the MWAA estimates are high! Then you are saying that you must be wrong. And you are throwing every insult at me, for failing to agree with you. What can I say.

Rob Whitfield

8:08 am on Sunday, November 4, 2012

The-stix, as you don't identify your real name or support for your claim to divine the truth, readers should discount your comments just as Bob Bruhn's Dulles Rail cost claims should be viewed with caution where not supported by hard facts.

From OIG report p8/9: "Between January 2009 and June 2011, MWAA awarded 190 contracts that exceeded $200,000—only 68 (36 percent) of which were awarded with full and open competition. Of these 190 contracts, 5 were sole source awards with a combined value of $6 million. However, MWAA awarded these five contracts without Board approval—which the Airports Act, lease agreement, and MWAA’s Contracting Manual require. MWAA awarded the remaining 117, or 62 percent of the 190 contracts over $200,000, using categorical exceptions ... these contracts amounted to $225 million, or 40 percent of the total value of ... contracts over $200,000. MWAA’s policies allow limited competition through the use of six categorical exceptions,...its Contracting Manual states...these exceptions “comprise only a small portion of the Airport Authority’s contracts and their dollar value.”

Overall Dulles Rail capital costs, including garages and other elements within the 2004 Environmental Impact Statement plus other transit station area improvements will cost over twice the original cost estimates from a decade ago. Projected Dulles Toll Road tolls are five times higher than forecasts made before MWAA became involved.

Reply
Comment_arrow

Bob Bruhns

12:27 pm on Sunday, November 4, 2012

By all means, people should not just take my word for it, but they should look at the costs for themselves. They should also take a look at the estimate offered by stix for the Rt 28 parking garage (he estimated $46.6 million in May 2012, when MWAA's March 6, 2012 estimate indicated $68.9 million - that's 48% higher than his estimate! Stix estimates that the cost should be 2/3 of what it is, I say it should be 1/2 of what it is, but we are BOTH showing that the cost should be much lower than it is! So why are we fighting among ourselves?

Rob Whitfield

8:34 am on Sunday, November 4, 2012

In early March 2012, I was warned by an official with knowledge of both Phase 1 and 2 cost estimates to review the assumptions made in estimating Phase 2 costs. While I was educated as a civil engineer and worked as an engineering consultant forty years ago, I lack the ability, time or funds to review the complex cost estimates.

Fairfax County, for whom Mark Canale works, did not provide to the public any detailed review and technical basis for support of the Phase 2 cost estimates. Canale merely acted as a rubber stamp. On the day prior to Fairfax County Board vote to support Phase 2 participation, I called the Fairfax County auditor who had reviewed Phase 1 numbers and assumptions circa 2010. He was not asked by the Fairfax BOS to review the Phase 2 cost estimate data.

The Dulles Corridor Advisory Committee, which is supposed to represent the public in Dulles Rail matters, did not request an independent review of costs.

In August 2011, I proposed a public oversight committee to include technically and financially qualified professionals to review and make suggestions for the Dulles Rail project and Dulles Airport area transportation improvements. Neither MWAA nor elected politicians have acted on this request.

When are we going to see a report showing both economic and financial feasibility of Phase 2, supported by all assumptions made? TIFIA loan funding of $1 to $2 billion would help reduce the potential DTR cost burden but who knows if that will happen.

Reply
Comment_arrow

Bob Bruhns

1:13 pm on Sunday, November 4, 2012

I agree with the folks at No Toll Increase that we should take the toll road back from MWAA now, while we have the chance. The Inspector General has shown violations of the agreement by which MWAA holds the road now, and the relatively high interest that MWAA will pay to bond for the bloated job costs that they and their estimators have handed us, suggests that we would do much better to finance them through Virginia or Fairfax and Loudoun Counties.

My problem with passing this to our government, is that our government is corrupt too, and taxpayers will be on the hook for the rather questionable prices of MWAA's contracts. This was exactly what we were promised would not happen! But if we are going to do this, we should do it immediately, before the refugees from the excessive tolls flood our local streets like Hurricane Sandy did to New York City, and before MWAA approves contracts at bloated prices, that were invited with bloated job estimates from MWAA and their cost estimators. Yes, I know that our so-called 'leaders' need perks and campaign contributions - but they also need votes. Stop the madness NOW!

And let's not stop there. WMATA is running Metro at such a high cost, that there is some $13.1 Billion in backlogged maintenance and capital needs. I'm sure that good old Northern Virginia will be tapped to pay for that - so let's clean up WMATA too!

Comment_arrow

the-stix

7:20 am on Monday, November 5, 2012

Mr. Whitfield, surely you are not saying that the estimates by rail project experienced AECOM and Parsons Brinkhoff and the independent estimator McDonough, Bolyard and Peck (as called for by DOT) are wrong are you? And you are not saying that the MWAA did not review the estimates, or if they did their review was flawed are you? And you are not saying the Commonwealth did not review the estimates are you?

Finally, can one not assume DOT reviewed the estimates and found them at least reasonable before La Hood offered his plan to reduce the MWAA part of Phase 2 (passing the cost of garages to the counties), and anounced the exact $ value of his plan?

I agree it is 'shameless' if Fairfax County on behalf of the tax payers did nothing with the estimate as I think you are saying. But if NO ONE looked critically at the AECOM and Parsons Brinkhoff and McDonough, Bolyard and Peck estimates then that would be news now would it not?.

Rob Whitfield

7:47 am on Monday, November 5, 2012

The-stix, MWAA certainly reviewed the estimates but at what level of detail I do not know. I never read the reports and data from AECOM/PB (it's Brinkerhoff!) or the independent estimator but was told to investigate the assumptions made in the estimates. I never have.

The Virginia agency responsible for reviewing the estimates is Department of Rail and Public Transportation. DRPT hired a professional engineer at the end of 2011, to work at the Tysons project office, presumably tasked with reviewing the data.

I have long had a high regard for Sam Carnaggio, the MWAA Phase 1 project manager. Pat Nowakowski, Executive Director for MWAA for Dulles Rail, has skated around various issues and questions in the past but at a meeting last week he did a good job in answering questions.

Reply

Rob Whitfield

8:10 am on Monday, November 5, 2012

It is hard for non-engineers to assess what risks are involved in a complex project such as Dulles Rail. The saying goes: "the devil is in the details." I am not a licensed PE so do not offer formal opinions in the engineering field.

It seems to me that the engineering and other risks associated with Phase 2 are less than they were for Phase 1. Also, a body of knowledge and experience has been built by the MWAA Project team over the last five years. The fundamental problems with Phase 2 continue to be the proposed financing structure and lack of evidence to support demand for heavy rail transit in the lower population and employment density areas westward from Reston into Loudoun County.

Add the potential negative real estate market impacts of sequestration and increased federal income taxes - $2,500 for those making $60,000 per year - coming in 2013 and we have a formula for potential financial disaster, not only for the Dulles Toll Road and Dulles Rail but for the Dulles Greenway also.

Several times in the past decade at Committee for Dulles and MWAA meetings, representatives of contractors and engineering consultants expressed concerns that the MWAA contract process was not handled fairly or properly. I did not have the ability to judge the reasonableness of these complaints so I took no action.

Here's a link to a Bacon's Rebellion article today about the OIG report on MWAA:

http://www.baconsrebellion.com/2012/11/the-mwaa-contracting-scandal.html

Reply

the-stix

8:14 am on Monday, November 5, 2012

Mr. Whitfield, you say you were trained as a civil engineer and worked as an engineering consultant. Phase 2 estimates were developed by rail experienced, professional and independent private consultants, each of whom has as a minimum their reputation on the line with this high profile construction program.

Question: in light of the actual costs being incurred on Phase 1, can you reasonably conceive that the current Phase 2 estimate is as much as 100% overpriced, even if a few of the assumptions are questionable?

I grant that the cost could be lower if program cost items were reduced or eliminated, but for the current work scope, is it even reasonable in your view for the estimate to be even near that far wrong? I am asking for your opinion as having related experience and a long personal involvement in these matters.

Reply
Comment_arrow

Bob Bruhns

11:58 am on Monday, November 5, 2012

I've been through this with stix on Restonweb for a long time. See the eighth post on this page, the documentation is there.
http://restonweb.com/forum/viewtopic.php?t=5977&start=45

Stix himself estimated a price for the Rt 28 parking garage that is about 2/3 of the one that comes from MWAA's estimators. He then bungled the percentage difference between his own May 24, 2012 estimate and the earlier July 3, 2011 FTA estimate, and now he will not admit that his own estimate is about 2/3 of the present MWAA estimate (from March 6, 2012), that I have to assume comes from the same estimating companes that he is extolling. He stands by his estimate, but their estimate is 48% higher than his, and yet he uses their numbers whenever it is convenient to him.

I am certainly not perfect or omniscient - but should people make a serious decision on the price of Dulles Rail, that will affect this region for generations, based on flip-flop stories from a pen-name poster?

Nobody is perfect. Why have our so-called 'leaders' not called on the cost estimators to justify their apparently excessive price estimates?

Regarding the cost estimating companies, see page 4 of my report.
http://www.bruhns.us/civic/DullesRail/Dulles-Rail---Silver-Line-overcost-report---Bruhns.pdf

Rob Whitfield

8:50 am on Monday, November 5, 2012

"The Stix" this is my final comment to you unless you divulge your identity.

Phase 1 costs rose signficantly from the 30% PE stage (2005?) to final design completion in 2009. Phase 1 projected capital costs rose from $1.5 billion in 2003 to $2,9 billion current cost estimate. MWAA projected Phase 2 at $2.5 billion in its 2006 submission to Virginia. By 2010, MWAA projected Phase 2 at $3.8 billion. Total new costs are still over $3 billion.

In Phase 1, as in Phase 2, some elements of the orginally approved "record of decision" plan were shed as costs rose, eg the $100 million Wiehle Avenue parking garage. The Wiehle garage project lacks any cost-benefit feasibility. Rather it is a politician's dream, paid for by taxpayers, by one who thinks that we should all ride transit, regardless of where we live or work.

Phase 2 will lack the complexities of utility relocation and right of way acquisition and easement issues in Phase 1. We are in a less competive global demand environment for raw materials today -concrete, steel etc- than in 2008 when the Peking Olympics and other major Chinese public works were a factor. That coupled with diminshed worldwide industrial and commercial development demand resulting from global economic woes indicates that the contractors bidding on Phase 2 will likely be less aggressive on pricing than would have been the case five years ago. As I recall, Bechtel/Dulles Transit Partners locked in Phase 1 contract price circa 2007.

Reply

the-stix

11:43 am on Monday, November 5, 2012

Thank you Mr. Whitfield, I am sorry you have an aversion to posters that do not identify themselves, but I do so for my personal security reasons and not at all because of any connection with you or your interests except in this forum.

I will say that I am disappointed that with your knowledge and experience you danced around my specific question. Phase 1 cost estimate changes during the preliminary engineering process, especially during a transition of project responsibility to MWAA are not surprising. The 100% PE estimate of $2.65 billion in 2006 is the project cost of record that carried forward to the project start and award of the Design/Build contract in 2007. That estimate was thoroughly reviewed and scrubbed by MWAA, DRPT (the Commonwealth), WMTAA and PMOC consisting of a variety of outside consultants and specialty experts (for the Tyson tunnel for example).

Except for project scope changes during the PE process, it is inconceivable that that Phase 1 100% PE estimate could be overpriced by a factor of two. In fact the recent cost estimate increase to $2.9 billion is clearly an indication that it was underpriced. I suggest that Phase 2 is and will be no different regarding costing integrity. Over 5 or 10% perhaps, but 100% over is not even a reasonable expectation except for scope changes. I should think anyone with any knowledge of the engineering estimating and contracting process of major programs would agree.

Reply
Comment_arrow

Bob Bruhns

12:30 pm on Monday, November 5, 2012

Stix, do you stand by your May 24, 2012 $46.6 million estimate for the price of the Rt 28 station? Because as of March 6, 2012, MWAA and (I have to assume) their cost estimators are saying something more like $68.9 million - which is 48% higher than your number. You were just saying 5% or 10% error might be realistic - but your own estimate says something else, doesn't it?

Rob Whitfield

1:09 pm on Monday, November 5, 2012

As those who know me can attest, I don't dance very well -especially around facts.
A minor correction; it's Parsons Brinckerhoff. the firm used to include Quade & Douglas. PB was acquired in 2009 by Balfour Beatty, a British company. In 2007, BB also acquired Centex Construction, Centex Homes commercial building division.

As to Phase 1 project costs, in his March 2, 2012 article, Terry Maynard of Reston 2020 tabulated the changes in cost estimates from the $1.52 billion noted in the Final EIS in 2004. The April 2006 FTA PMOC shows $2.07 billion "true 100% PE costs" with a 2011 completion date. By July 2007, the FTA "updated 100% PE" shows $2.65 billion and 2013 completion date.

http://reston2020.blogspot.com/2012/03/key-dulles-rail-cost-document-held.html

As to the level of Phase 2 review conducted by MWAA and DRPT, MWAA only took one week from receiving the project cost estimate data from the consultants on or about March 1, 2012 before releasing information to its project partners -Fairfax and Loudoun counties. As Terry points out, most Fairfax County Supervisors did not want to wait to review the data before approving its Phase 2 participation.

Taxpayers in Fairfax and Loudoun counties should demand a greater role in the Phase 2 project oversight and decision making process, either adding public representation by professional experts in finance, engineering and other skills to the existing Dulles Corridor Advisory Committee or through a new committee.

Reply

the-stix

2:26 pm on Monday, November 5, 2012

I am familiar with Maynard’s post. As I said earlier, the cost growth of Phase 1 should not be surprising as the project requirements and scope are refined from start, through 50% PE completion to 100% PE completion. Also with all the program delays affecting project start and completion dates, one can reasonably expect cost escalation. Finally I have never been convinced that there was not just a bit of politics involved to keep the initial estimates down pre-MWAA, for the public consumption and probably for the project to look more attractive to DOT to maximize their contribution.

As to Phase 2, I am certainly in favor of more transparency and of some public explanation of the project cost estimates. I do not favor the public having a significant role in the “decision making process”. I have run a few major programs in my time and can attest that “too many cooks spoil the broth”. And I expect this would be especially true of “public” cooks who are often excessively vocal but woefully ignorant. One needs only look at some of the posters in the Patch forums to see what I mean.

Bottom line, based on the actual costs being incurred on Phase 1, I am relatively confident that The Phase 2 100% PE estimate is not all that far off from today’s reality for heavy rail construction. Just an opinion to be verified.

Reply
Comment_arrow

Bob Bruhns

9:26 am on Tuesday, November 6, 2012

Congratulations, stix. Given that the official parking garage cost estimate is 35% higher than you were able to balloon your own parking garage cost estimate, it is refreshing to see that you support a public explanation of the project cost estimates for Phase II, at least. I thought you would simply continue to negate your own analysis by using the estimators as a reference for the estimators, much as one of Fairfax County's Dulles Rail Project Managers previously used Metro prices to justify Metro prices.

joe brewer

9:40 am on Tuesday, November 6, 2012

Once Mr. Brown gets through wiping it off his face he can then spend his time looking for other gainful employment.

Reply
Comment_arrow

Bob Bruhns

3:51 pm on Tuesday, November 6, 2012

Agreed. The interference that Mr. Brown disliked, was very well justified.

Just the Facts

10:10 am on Tuesday, November 6, 2012

I have so many questions I don't know where to start. Who benefited from these contracts? What department (s) gave out these contracts? What role does the CEO have in approving contracts ? Does the staff have authority to just give out contracts without CEO or Board approval? Why did they not report who was awarded all these contracts? Why is Wolf, McDonnell and LaHood not asking for any resignations? Im sick of this I'm sorry crap we will fix it going forward. I will be paying huge tolls and these jerks just keep saying I'm sorry we will adopt a new policy. People in leadership need to be fired. Where are our elected leaders? I have not heard one of them Republican or Democrat ask for any resignations. WHY???

Reply
Comment_arrow

Bob Bruhns

10:53 am on Tuesday, November 6, 2012

Well, Governor McDonnell asked for Dennis Martire's resignation (and got it). And a former MWAA Vice President, Arl Williams, very recently resigned just before this audit report was released.

Transportation Department Audit On MWAA Finds Violations
WAMU, November 1, 2012
http://wamu.org/news/12/11/01/transportation_department_to_release_audit_on_silver_line_project

I'd say the title of that article puts it ... a bit mildly. :)

What we are seeing, I think, is a fight between high level crooks for control of the Billion and a half dollars of overcharge in the Phase II contracts. We get stunning report after stunning report, including this audit that shows MWAA routinely paying 1.3 to 3.3 times as much as they should pay for some big priced contracts - and yet there is NO discussion of the apparent double price of the Dulles Rail job.

I assert that the intention is simply to grab that extra Billion and a half dollars, in order to give it to different chosen beneficiaries, rather than back to the public that must pay for it all. And I am glad that more and more people are starting to see that.

Comment_arrow

Bob Bruhns

3:48 pm on Tuesday, November 6, 2012

Also, I found this. It is a later edition of the November 1, 2012 Martin Di Caro article. Apparently MWAA's Vice President for information and telecommunications was fired this past spring for receiving two tickets to the 2009 Super Bowl (and other expensive gifts) from a contractor.

Audit Exposes Litany of Shady Dealings by Agency Running D.C. Area Airports
Transportation Nation, November 2, 2012
http://transportationnation.org/2012/11/02/litany-of-shady-dealings-exposed-in-agency-running-d-c-airports/

Just the Facts

10:16 am on Tuesday, November 6, 2012

Also I would assume MWAA does an audit every year. Why was this never discoved before this report? Please fire someone just to show that you cut the head of this snake. If our elected leaders do not get involved and ask for resignations then they are part of the problem.

Reply

joe brewer

4:34 pm on Tuesday, November 6, 2012

I do believe they do a internal audit. This quagmire dates back to the 90's. The whole concept of a Authority is a failed system, they are from the school of blame he did it, or she did it and they didn't have the authority yet they awarded contracts under the current group of leaders. The buck stops with them no if's and's or but's about it. Let me reconsider I do believe there are some butts involved.

Reply
Comment_arrow

Bob Bruhns

9:39 am on Wednesday, November 7, 2012

MWAA has an Audit Committee that was co-chaired by two former Board members, but its meetings were held in secret during the entire period of this recently completed US DOT Audit. The Inspector General commented that this was ironic, given its function.

The MWAA Board and Officers were a happy bunch of dubious political appointees playing all kinds of hidden games, until Frank Wolf and Tom Latham requested this US DOT audit last year. From comments I have read, MWAA and its Board and Directors complained, resisted and balked, but the truth is finally coming out. Potter remains, even though he disgraced himself in the Reiley hiring, and Curto remains, even though he has been a front for the nonsense that went on. Tom Davis had the right enemies on the MWAA Board - witness they grabbed his papers and misused the information in them. But he should have been blowing a great big whistle, and I never heard it.

The Dulles Toll Road should be taken back by Virginia DOT, and Dulles Rail Phase II should be supervised by a much better group.

Comment_arrow

Bob Bruhns

3:28 pm on Wednesday, November 7, 2012

Wolf Statement On DOT IG Report On MWAA
Congressman Wolf's Website, November 01, 2012
http://wolf.house.gov/press-releases/wolf-statement-on-dot-ig-report-on-mwaa/

Just the Facts

11:41 pm on Sunday, December 9, 2012

Frank Wolf was very vocal about Martire's plane ticket but has been silent on the 180k job for a no show job for a former Board member. He also held that lame press conference with Senator Allen and Barbara Comstock complaining about MWAA hiring Mame Reiley while wearing George Allen for Senate stickers. Was this a press inference about MWAA or a political event for Allen? Either way it looked like they made the deal political. Now that the elections are over Wolf and McDonnell have been silent. It just shows most of this has been political theatre. These politicians have no interest in cleaning up MWAA? They just want to use them to beat up on. Fire the three clowns and I will think MWAA has a hance to survive. Potter, Davis and Curto need to resign.

Reply

Rob Whitfield

5:56 am on Monday, December 10, 2012

At the November 16 hearing by the House Transportation and Infrastructure Committee on the USDOT Inspector General's audit of MWAA. nobody involved escaped without blame for shortcomings and misconduct. The USDOT IG Calvin Scovel was very professional in his presentation. He did not comment on the FBI's investigation of MWAA.

At the Governor's Transportation Conference in Tysons last week, nobody offered substantive comment on the as yet unresolved feasibility and financial problems for Dulles Rail Phase 2. My view is that it is time for the USDOT IG Scovel to tackle the many as yet unreported problems at the Washington Metro Area Transit Authority.

WMATA has yet to admit publicly that upgrading traction power stations in Arlington and DC plus other improvements needed to downtown elevators and escalators to allow more eight car trains to operate there will cost well over $1 billion.

The Dulles Airport maintenance yard has been sized and designed for all Series 7000 rail cars - not just those to be used by Dulles Rail. WMATA is trying to force Virginia taxpayers to pay all of its costs instead of most being paid by Metrorail riders. A total absence of leadership exists by both Republicans and Democrats.

Why has no elected official or transportation agency leader demanded independent forecasts of Metrorail ridership, revenues and cost projections for the Silver Line? The project is the biggest financial boondoggle in Virginia history.

Reply

Bob Bruhns

12:30 pm on Tuesday, December 11, 2012

It's just a bunch of crooks fighting over stolen money. Reports that expose their lies are not going to help them grab the money and run, so they don't demand them.

The Dulles Rail project, also known as the Silver Line, costs two times what it should - we're talking about an unnecessary extra $2.5 to $3 Billion dollars of economic drain that is causing a major financial crisis for this entire region. And then there are the finance charges for the money that we need to borrow, to pay the bloated costs of this project. And let's not forget the real and needed projects that must make do on less money, because so much is being devoured by this ripoff.

When are people going to wake up?

Reply

Leave a comment